An example sequence and duration of FRCS activities during design and construction is outlined in Table 1.
Table 1 Typical Sequence of FRCS Design and Construction Activities
Activity / Lead | New Project | Renovation Project | Typical Duration |
Presolicitation RFP Considerations | Obtain the Regional and ESTCP Platform Enclaves catogorization and categorize the FRCS Use the EI&E FRCS Master Control List for C-I-A Values and Information/Data Types | Obtain the Regional and local Platform Enclaves catogorization and categorize the FRCS Use the EI&E FRCS Master Control List for C-I-A Values and Information/Data Types | NA |
Design
Lead: A/E Documents/Models/Tools:
| FRCS front end or new susbsystem back end to connect to front end Confirm/revise system categorization, define network architecture, system components, concept of operations, drawings, and specifications. At 90% design create initial SSP and baseline security risk assessment. | FRCS front end upgrade or subsystem modernization Confirm/revise system categorization, define network architecture, system components, concept of operations, drawings, and specifications. At 90% design create initial SSP and baseline security risk assessment. | 3-6 Months |
Construction Test and Development (T&D) and Patch Management Environments (Virtual or Physical) Lead: Construction/System Integrator Documents/Models/Tools:
| Conduct FRCS build and patch activities without impacting the organization’s production systems (test and development environment typically provided by vendor). | Validate and verify the upgrade/modernization/ patch is ready to support the additional systems without impacting the organization’s production systems (test and development environment typically provided by vendor). | 4 – 6 weeks |
Construction Build/Configure Servers | Build and/or configure servers to properly operate the FRCS solution. | Build and/or configure servers to properly operate the FRCS solution. | 1 – 2 weeks |
Construction Install Supporting Software Lead: Construction/System Integrator | Install supporting software on FRCS servers. | Install supporting software on FRCS servers. | 1 – 2 weeks |
Construction Configure Supporting Software Lead: Construction/System Integrator Documents/Models/Tools:
| Configure FRCS software to meet unique needs. After the operating system is loaded, apply hardening criteria (STIGs), run Security Content Automated Protocol (SCAP)-validated tool, perform factory acceptance testing (FAT) on major system components and devices, perform initial penetration testing. | Configure FRCS software to meet unique needs. After the operating system is loaded, apply hardening criteria (STIGS), run Security Content Automated Protocol (SCAP)-validated tool, perform FAT on major system components and devices, perform initial penetration testing. | 1 – 2 weeks NOTE: If a vendor will be creating a STIG for the UMCS Front-End or lower Level devices, this process can take several months to a year. Apply STIGS to the PE and isolate lower Levels until vendor STIGS are approved. |
Construction Implement and assess security controls Lead: construction/system integrator Documents/Models/Tools:
| Conduct RMF Steps 3 and 4 by applying controls identified during the requirements and design phase, by assessing the adequacy and effectiveness of security controls, and by documenting findings in the security assessment report. Create draft approval package. | Conduct RMF Steps 3 and 4 by applying controls identified during the requirements and design phase, by assessing the adequacy and effectiveness of security controls, and by documenting findings in the security assessment report. Create draft approval package. | 12 – 20 weeks |
Conduct testing on initial build Lead: construction/system integrator Documents/Models/Tools:
| Test FRCS solution in a test and development environment to ensure system errors are found, corrected before solution is deployed on network. | Test FRCS solution in a test and development environment to ensure system errors are found, corrected before solution is deployed on network. | 2 – 4 weeks |
Construction - conduct pilot implementation deployment Lead: construction/system integrator Documents/Models/Tools:
| Pilot implementation of FRCS solution on a small subset of user base to evaluate solution against real-world requirements. Conduct site acceptance testing, and if required final penetration testing, and create final approval package. | Conduct site acceptance testing, and if required final penetration testing, and create final approval package. | Varies with size of deployment (number of facilities and interconnections) |
Receive Authorization (ATO) and move to production Lead: construction/system integrator Documents/Models/Tools:
| Deploy the FRCS to full production and implement continuous monitoring. | Deploy the FRCS to full production and extend continuous monitoring to new systems. | NA |